# Buying from a developer in North Cyprus: what people find out too late

New builds in North Cyprus are usually bought years before completion. During construction everything looks simple: a payment plan, a promised date, attractive renderings. The problems start at handover: the property is finished late, payments appear that were never agreed, and what you get is not quite what you expected.

Below is what to find out and get in writing **before** you sign the sales agreement, and what to do if you are already at the handover stage. The list is based on real owners' experiences.

## 0. The agreement itself: what to read before signing

Many handover problems are already in the sales agreement; nobody read that part. Check in advance:

- **Language versions.** The agreement is often bilingual: Turkish plus English or Russian. Translations can be incomplete: for example, the Turkish text says the annual maintenance fee is paid in full at the start of each year, and the translation leaves that out. Find out which version prevails and, if needed, get an independent translation of the Turkish text.
- **Keys "in exchange for" the maintenance agreement.** Some agreements state that the handover act will not be issued until the buyer signs the handover documents, including the maintenance agreement. That gives the developer legitimate leverage at handover. Discuss it before you buy and, if possible, ask for the draft maintenance agreement to be attached to the sales agreement.
- **When maintenance fees start.** It may be the key handover date, or it may be "completion of construction and commissioning of the complex" — that is, before you get the keys.
- **Insurance.** The obligation to insure the property may start on the completion date, not at key handover.
- **Resale before title transfer.** It is often allowed only with the developer's consent and for a separate fee. If you are buying to resell, find out the terms in advance: in a dispute this is strong leverage for the developer.
- **Notices.** The agreement may treat WhatsApp or e-mail messages as valid notice. A manager's message in a chat can then be a formal demand with a deadline.
- **Registration.** Find out whether the agreement has been registered (stamped) at the Land Registry: your protection depends on it, and sometimes so does the electricity connection.
- **Who signs.** If an agent signs for you under a power of attorney, keep the power of attorney and a copy of the signed agreement.
- **Unit number.** The apartment or villa number in the agreement and in the land registry may differ. At handover, ask for written confirmation that they are the same property.

## 1. Compensation for late completion

Completion dates in North Cyprus often slip. A good agreement provides for this: after the promised date and a grace period, the developer pays compensation for each month of delay, usually a percentage of the price.

**Before buying, check:**
- whether the agreement provides compensation for delay, and how much;
- how long the grace period is and from which day it runs;
- what counts as "completion": ready for handover, final inspection, or key handover.

**At handover:**
- **Claim the compensation.** If the deadline was missed, compensation is due under the agreement. Many owners forget about it, and developers don't offer it.
- **Keep all of the developer's messages.** Their own messages are the best evidence of dates: "the villa isn't ready, the front door hasn't been installed", "ready" (followed by an inspection with a list of defects), "defects fixed". A declared "ready" is not completion if the inspection finds defects.
- **Count precisely, including part months.** The developer may offer "3 months" when the dates give 3 months and 12 days.
- **Get the readiness date in writing.** For example, a message from the developer that the final inspection has taken place and all defects have been fixed. Both the compensation and the start of maintenance fees are counted from this date.
- **Set-off.** You can discuss with the developer setting the compensation off against a payment you owe them. Propose it in writing.
- **If you take the keys before this is settled,** sign the handover act with a note that your compensation claim is reserved.

## 2. Specification: what exactly is included

"Turnkey" means very different things to different developers. Built-in furniture, appliances, air conditioning, mosquito screens, wardrobes, finishes, sanitary ware, water and electricity connections — any of these may be included in the price or turn up as an extra charge at handover.

**Before buying, ask for:**
- **an annex to the agreement with the full specification**: what is installed, ideally with brand and model, or at least the class;
- what happens with water and electricity connections and meters: included in the price, or charged separately, and how much;
- **a complete list of payments at handover**: everything the developer will invoice apart from the price, with amounts.

Anything not in the agreement and its annexes is very hard to prove later.

## 3. Extras imposed at handover

A typical situation: at handover the developer adds equipment or works to your bill that the agreement says nothing about.

**What to do:**
- **Check the agreement and all its annexes.** If there is no obligation to pay, you are entitled to refuse.
- **The developer's arrangements with its contractors don't bind you** if you weren't part of them. You have paid for the property, and you are free to choose the equipment and the supplier yourself.
- **Ask in writing for the amount to be removed** from the payments for your property.
- **Ask for written confirmation that refusing will not affect** key handover, title transfer or the developer's consent to a resale. Where the agreement requires that consent, it is a common pressure point.
- If you do want the equipment, ask for a quotation and compare it with other suppliers.

## 4. Maintenance fees and the maintenance agreement

Common situations at handover:
- **you are asked to pay a year of maintenance in advance before key handover**, although the maintenance agreement says payment is due at handover;
- **charges are backdated**: you are told that "maintenance started" on a date that has already passed, while defects were still being fixed;
- **you receive a notice threatening legal action, interest and penalties** with a 10-day deadline.

What to do: compare the demand with both agreements (sales and maintenance), ask for the calculation (budget) behind the amount, propose that the first maintenance year runs from the actual readiness date, and reply in writing within the deadline. Do not ignore a notice threatening legal action: legal costs and penalties can easily exceed the amount in dispute.

At handover the developer almost always asks you to sign a maintenance agreement for the complex: pool, cleaning, security, gardens, lighting. The terms can be very one-sided: the fee can be raised at any time, penalties and high interest apply only to the owner, and the agreement cannot be ended even after a sale.

A detailed breakdown is on a separate page: ["Maintenance agreements: what to check before buying"](/en/guide/maintenance-agreement).

The key point: **make sure key handover does not depend on signing the maintenance agreement** as drafted. If your sales agreement says otherwise (see section 0), negotiate changes before you buy.

## Handover inspection

- **Carry out a final inspection** yourself or through a representative and list the defects. Ask for written confirmation that they have been fixed.
- **Signing the handover act does not mean giving up claims** about quality. If time has passed between the final inspection and key handover, state in a letter or in the act that the developer is responsible for the property's condition until handover, and that defects found at handover will be fixed under the agreement.
- If some issues are not settled (compensation, extra charges), sign the act **with a written reservation** that your claims are preserved.

## If the developer proposes a settlement agreement

That's a good sign, but the developer usually drafts it. Before signing, check:

- **The amount and calculation.** Check the dates and the arithmetic, including part months.
- **The exchange rate.** If the compensation is in euros and the fee in pounds, a rate "agreed by both parties" invites a new dispute. An objective rate is better: for example, the Central Bank of Turkey or the European Central Bank rate on the date of signing.
- **The scope of the waiver.** Wording such as "full and final settlement of all claims" can take away your rights regarding defects and warranty. The waiver should cover only compensation for the delay, and your rights on quality and warranty should be expressly preserved.
- **Confirmation that nothing else is owed.**
- **All extras not provided for in the agreement are removed**, and this does not affect handover, title transfer or consent to a resale.
- **Handover is not tied to signing the maintenance agreement**, and key handover does not depend on it.

## If you can't reach agreement

A fallback is to **pay the disputed amount "under protest"** (without prejudice), with a written note that all your rights and claims are preserved. You get the keys and are free to use or sell the property, and you pursue the compensation separately. Check with a lawyer how to word this in your case.

## How to correspond with the developer

- **Everything in writing.** Verbal promises from managers count for nothing in a dispute.
- **One letter covering all issues**: completion date, compensation, maintenance fee, maintenance agreement, extras. The issues are linked, and raised separately they easily get lost between departments.
- **Ask for one written reply on behalf of the company**, not from different departments and staff.
- **Refer to the clauses of the agreement**: the clause number and what it says.
- **Show that you want an amicable solution.** For example, propose setting off the compensation against payments, and confirm you are willing to pay for services actually provided.
- If the amount is significant, **involve a lawyer** — in Cyprus or where you live.

## Questions and answers

**Am I entitled to compensation if the developer finished late?**
If the agreement provides for it, yes. Check the clauses on the completion date and compensation, count from the end of the grace period and calculate the amount. Developers usually don't remind you.

**Can I set the compensation off against payments to the developer?**
You can propose it in writing, but there is no guarantee. It is best if the developer confirms the set-off in writing before key handover.

**The developer wants extra payment for services or equipment that aren't in the agreement. What should I do?**
Check the agreement and annexes. If there is no obligation to pay, ask in writing for the amount to be removed and for confirmation that this will not affect key handover or title transfer.

**What should the specification annex include?**
Everything installed in the property: appliances (water heater, air conditioning — indoor and outdoor units — and so on), kitchen, sanitary ware, finishes, plus water and electricity connections and meters. And a complete list of payments at handover.

**The developer wants maintenance paid in advance before key handover. Is that allowed?**
It depends on your agreement. Compare the sales agreement (in every language version) and the maintenance agreement: when the fee is payable and from what date it is charged. If the maintenance agreement says "at key handover", advance payment before handover contradicts it. Reply in writing within the deadline and ask for the calculation.

**Can I take the keys while the dispute is unresolved?**
You can try to sign the handover act with a written reservation that your claims (compensation, defects, extras) are preserved. Check with a lawyer how best to word it in your case.

---

*This is not legal advice. Agreements differ between developers. Show the agreement to a lawyer before signing and in any dispute.*