Buying from a developer in North Cyprus: what people find out too late

New builds in North Cyprus are usually bought years before completion. During construction everything looks simple: a payment plan, a promised date, attractive renderings. The problems start at handover: the property is finished late, payments appear that were never agreed, and what you get is not quite what you expected.

Below is what to find out and get in writing before you sign the sales agreement, and what to do if you are already at the handover stage. The list is based on real owners' experiences.

0. The agreement itself: what to read before signing

Many handover problems are already in the sales agreement; nobody read that part. Check in advance:

1. Compensation for late completion

Completion dates in North Cyprus often slip. A good agreement provides for this: after the promised date and a grace period, the developer pays compensation for each month of delay, usually a percentage of the price.

Before buying, check:

At handover:

2. Specification: what exactly is included

"Turnkey" means very different things to different developers. Built-in furniture, appliances, air conditioning, mosquito screens, wardrobes, finishes, sanitary ware, water and electricity connections — any of these may be included in the price or turn up as an extra charge at handover.

Before buying, ask for:

Anything not in the agreement and its annexes is very hard to prove later.

3. Extras imposed at handover

A typical situation: at handover the developer adds equipment or works to your bill that the agreement says nothing about.

What to do:

4. Maintenance fees and the maintenance agreement

Common situations at handover:

What to do: compare the demand with both agreements (sales and maintenance), ask for the calculation (budget) behind the amount, propose that the first maintenance year runs from the actual readiness date, and reply in writing within the deadline. Do not ignore a notice threatening legal action: legal costs and penalties can easily exceed the amount in dispute.

At handover the developer almost always asks you to sign a maintenance agreement for the complex: pool, cleaning, security, gardens, lighting. The terms can be very one-sided: the fee can be raised at any time, penalties and high interest apply only to the owner, and the agreement cannot be ended even after a sale.

A detailed breakdown is on a separate page: "Maintenance agreements: what to check before buying".

The key point: make sure key handover does not depend on signing the maintenance agreement as drafted. If your sales agreement says otherwise (see section 0), negotiate changes before you buy.

Handover inspection

If the developer proposes a settlement agreement

That's a good sign, but the developer usually drafts it. Before signing, check:

If you can't reach agreement

A fallback is to pay the disputed amount "under protest" (without prejudice), with a written note that all your rights and claims are preserved. You get the keys and are free to use or sell the property, and you pursue the compensation separately. Check with a lawyer how to word this in your case.

How to correspond with the developer


This is not legal advice. Agreements differ between developers. Show the agreement to a lawyer before signing and in any dispute.

Questions and answers

Am I entitled to compensation if the developer finished late?

If the agreement provides for it, yes. Check the clauses on the completion date and compensation, count from the end of the grace period and calculate the amount. Developers usually don't remind you.

Can I set the compensation off against payments to the developer?

You can propose it in writing, but there is no guarantee. It is best if the developer confirms the set-off in writing before key handover.

The developer wants extra payment for services or equipment that aren't in the agreement. What should I do?

Check the agreement and annexes. If there is no obligation to pay, ask in writing for the amount to be removed and for confirmation that this will not affect key handover or title transfer.

What should the specification annex include?

Everything installed in the property: appliances (water heater, air conditioning — indoor and outdoor units — and so on), kitchen, sanitary ware, finishes, plus water and electricity connections and meters. And a complete list of payments at handover.

The developer wants maintenance paid in advance before key handover. Is that allowed?

It depends on your agreement. Compare the sales agreement (in every language version) and the maintenance agreement: when the fee is payable and from what date it is charged. If the maintenance agreement says "at key handover", advance payment before handover contradicts it. Reply in writing within the deadline and ask for the calculation.

Can I take the keys while the dispute is unresolved?

You can try to sign the handover act with a written reservation that your claims (compensation, defects, extras) are preserved. Check with a lawyer how best to word it in your case.